The contractor and utility companies will continue installing drainage structures, transferring utility cables, relocating a water main on Mascoma Street, and working on the stone retaining wall. The pedestrian detour for the project has changed to accommodate work on the Mechanic Street side. Pedestrians will be directed to cross through the center of the roundabout with assistance from flaggers. Please expect delays and use caution in the work zone.